{"id":"france-nexans-mallorca-menorca-preferred-supplier-20261022","canonicalSlug":"france-nexans-mallorca-menorca-preferred-supplier-20261022","url":"https://wellficent.com/en/news/france-nexans-mallorca-menorca-preferred-supplier-20261022","language":"en","title":"Nexans selected for Mallorca–Menorca power cable project","summary":"Red Eléctrica chose Nexans as preferred supplier for a 132 kV link between the Balearic islands; a six-month engineering phase is to precede any EPCI contract.","body":["Nexans said on 22 October that Red Eléctrica, the Spanish grid operator owned by Redeia, selected it as preferred supplier for the Mallorca–Menorca 3 interconnection. The proposed 132 kV HVAC system would combine subsea and land cables.","The tender terms provide for a six-month collaborative engineering phase to lay the groundwork for a later engineering, procurement, construction and installation contract. Nexans described delivery as planned to start in mid-2027. The selection is not a signed EPCI contract or completed cable delivery; the project is in Spain, although Nexans is a French issuer."],"keyPoints":[],"sections":[],"text":"Nexans selected for Mallorca–Menorca power cable project\n\nRed Eléctrica chose Nexans as preferred supplier for a 132 kV link between the Balearic islands; a six-month engineering phase is to precede any EPCI contract.\n\nNexans said on 22 October that Red Eléctrica, the Spanish grid operator owned by Redeia, selected it as preferred supplier for the Mallorca–Menorca 3 interconnection. The proposed 132 kV HVAC system would combine subsea and land cables.\n\nThe tender terms provide for a six-month collaborative engineering phase to lay the groundwork for a later engineering, procurement, construction and installation contract. Nexans described delivery as planned to start in mid-2027. The selection is not a signed EPCI contract or completed cable delivery; the project is in Spain, although Nexans is a French issuer.","category":"business","region":"world","topics":["power","electrical-materials"],"eventDate":"2026-10-22","eventDateBasis":"source-publication-date","publishedAt":"2026-10-22T12:27:30Z","modifiedAt":"2026-10-22T12:27:30Z","publicationBasis":"first-publication","preparedAt":"2026-10-22T12:25:27Z","sourcePublishedAt":"2026-10-22","translatedAt":"2026-10-22T12:24:05Z","sources":[{"url":"https://www.nexans.com/press-releases/preferred-supplier-for-strategic-mallorca-menorca-power-cable-project/","name":"Nexans","checkedAt":"2026-10-22","attribution":"Nexans release dated 2026-10-22; facts paraphrased. No source prose or media reproduced. No open reuse licence identified.","publishedAt":"2026-10-22"}],"translations":{"en":"https://wellficent.com/en/news/france-nexans-mallorca-menorca-preferred-supplier-20261022","tr":"https://wellficent.com/tr/news/france-nexans-mallorca-menorca-preferred-supplier-20261022","ar":"https://wellficent.com/ar/news/france-nexans-mallorca-menorca-preferred-supplier-20261022","fr":"https://wellficent.com/fr/news/france-nexans-mallorca-menorca-preferred-supplier-20261022","es":"https://wellficent.com/es/news/france-nexans-mallorca-menorca-preferred-supplier-20261022","ru":"https://wellficent.com/ru/news/france-nexans-mallorca-menorca-preferred-supplier-20261022","pt":"https://wellficent.com/pt/news/france-nexans-mallorca-menorca-preferred-supplier-20261022"},"corrections":[],"locations":[],"type":"news","classification":{"version":"1","dataKinds":["project-update"],"geographies":[{"role":"economic-scope","countryCode":"ES","subdivisionCode":null},{"role":"issuer-location","countryCode":"FR","subdivisionCode":null}],"evidenceBasis":["agreement","plan"],"measurementPeriod":null}}