Aker Solutions’ June 29 release reports Tussa Energi’s electromechanical equipment award for Norway’s Tussa II plant. Two 75 MW Pelton units are planned.

This is equipment delivery; it does not assign all civil construction to the same company. Technical assessment should coordinate acceptance tests for turbines, generators and grid connection. Planned installed capacity is a different measure from achieved annual electricity production.