Afghanistan’s Mines and Petroleum Ministry reported on September 15 that 122.3 kilometres of the Herat TAPI section had been welded and laid, roughly 80% of that work component.
Burial covered 71.5 kilometres and hydrostatic testing 33 kilometres. Herat distribution-network design continues. These distinct stages mean the percentage does not represent commissioning of the entire TAPI pipeline.
Optional first-party analytics records page activity, device/browser details and performance after you accept. IP addresses are encrypted and retained for 7 days; other measurements for 90 days. You can withdraw consent in Privacy choices.
Google Analytics starts only after you accept analytics. Google receives page views, engagement, browser/device details and your connection IP. Analytics cookies last up to 180 days. Search text, URL query strings and referrer paths are excluded. Advertising signals are disabled. You can reject or withdraw in Privacy choices. How Google uses data