Story details

The screening resolution is dated 28 September and was published in the BOE on 10 October. The project concerns the GJ-10 corridor between Lloreda and Veriña, linking the port and the ZALIA logistics area; the document cites traffic of about 30,000 vehicles a day on the existing corridor.

The decision requires a fuller assessment; it is not project approval. The screening document identifies information gaps, including the unresolved junction alignment with a linked boulevard and the absence of an invasive-species study, and says significant environmental effects cannot be excluded at this stage.